Work Item |
Item Type |
Event or Activity |
Date |
Status/Notes |
|
GovOMG |
WP |
Review RFI Drafts |
20071211
thru
20080825 |
In Process
20071211: Reviewed by GovDTF in Burlingame.
Review drafts circulated April 2008 |
|
RMS |
RFP |
LOI to Submit Due |
20080801 |
|
|
MBA |
RFI |
First Draft of refocused RFI |
20080811 |
In Process |
|
MBA |
RFI |
Review RFI Drafts |
20080822 |
20071211: Reviewed by GovDTF in Burlingame
and refocused.
20070924: Reviewed by GovDTF in Jacksonville |
|
RMS |
RFP |
Revised Submissions due and placed on OMG
document server |
20080825 |
Four week rule for Orlando |
|
GovOMG |
WP |
Post Final Draft of Whitepaper |
20080825 |
4-wk Rule for Orlando Meeting |
|
Skills RFP |
RFP |
Draft RFP posted to OMG Document Server |
20080825 |
(4-week Rule for Orlando) |
|
FTF-FTF |
FTF |
Report Posting |
20080825 |
4-week rulefor Orlando Meeting |
|
MBA |
RFI |
Post Final RFI |
20080825 |
4-week rule for Orlando meeting |
|
OMG TC Meeting, Orlando
Florida |
|
|
20080923 |
|
|
RMS |
RFP |
Revised Submission presentations |
20080923 |
GovDTF Plenary, Orlando |
|
RMS |
RFP |
Final evaluation and selection by TF
Recommendation by the GovDTF to AB and TC |
20080923 |
|
|
GovOMG |
WP |
Issue Whitepaper |
20080923 |
GovDTF Plenary, Orlando Meeting |
|
Skills RFP |
RFP |
GovDTF Review of Draft RFP |
20080923 |
|
|
MBA |
RFI |
Approval of RFI by GovDTF |
20080923 |
GovDTF Plenary, Orlando TC Meeting |
|
RMS |
RFP |
Approval by Architecture Board. Review by
TC |
20080925 |
|
|
MBA |
RFI |
Approval of RFI by Architecture Board |
20080925 |
|
|
RMS |
RFP |
TC votes to recommend specification |
20080926 |
DTC Electronic Vote Begins. Takes nominally
10 weeks |
|
MBA |
RFI |
Issuance of RFI by Domain Technology
Committee |
20080926 |
DTC Plenary, Orlando TC Meeting |
|
FTF-FTF |
FTF |
Report Deadline |
20081003 |
1-week after Orlando
Represents FTF Expiration |
|
Skills RFP |
RFP |
Final RFP posted to OMG Document Server |
20081110 |
(4.week Rule for Santa Clara) |
|
Skills RFP |
RFP |
Architecture Board Review and Approval |
20081208, 20081211 |
8,11-December-2008 |
|
Skills RFP |
RFP |
GovDTF Vote to Recommend Issuance |
20081209 |
GovDTF Plenary, Santa Clara |
|
Skills RFP |
RFP |
Domain Technology Committee Vote to Issue
the RFP |
20081212 |
|
|
Skills RFP |
RFP |
Initial Submission Due Date |
20090223 |
(4-week Rule for Washington DC) |
|
Skills RFP |
RFP |
Letters of Intent Deadline |
20090320 |
(Immediately before Washington DC) |
|
Skills RFP |
RFP |
Initial Submission Presentations and
Evaluation by the GovDTF |
20090324 |
(GovDTF Plenary, Washington DC) |
|
Skills RFP |
RFP |
Voting Registration Closes |
20090413 |
(Immediately before Washington DC) |
|
Skills RFP |
RFP |
Revised Submission Due Date |
20090525 |
(4-week Rule for June Meeting) |
|
Skills RFP |
RFP |
Final Evaluation and Selection by GovDTF |
20090623 |
(GovDTF Plenary) |
|
Skills RFP |
RFP |
Architecture Board Approval |
20090625 |
|
|
Skills RFP |
RFP |
Domain Technology Committee Recommendation
to Issue |
20090626 |
(Beginning of electronic voting, nominally
a 10 week period) |
|
Skills RFP |
RFP |
Board of Directors Issues Specification |
20090701 |
Date is nominal. Board Meeting
following DTC Recommendation (or prior to,
but contingent on recommendation) |